Administration of nature and forests

  • Project type : New Construction
  • Building Type : Office building < 28m
  • Construction Year : 2012
  • Delivery year : 2015
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.
  • Net Floor Area : 2 750 m2
  • Construction/refurbishment cost : 7 500 000 €
  • Number of Work station : 78 Work station
  • Cost/m2 : 2 727 €/m2
  • Cost/Work station : 96 154 €/Work station


Moderated by : Sylvain Bosquet

Similar case studies

Mosaic Centre for Conscious Community and Commerce

​The Mosaic Centre for Conscious Community and Commerce is going to more than an office building.  This new, 3000 m2 building will be located at the threshold of a commercial strip and the emerging Edmonton community of Summerside (...)

Kuggen. Ecopilot, energenious building automation system

​KabonaABKabona is a company which works with energenious energy building automation and the company’s head office is locatedin Borås, Sweden. Kabona was founded in 2001 and has long-standing and solidexperience, which has formed the (...)

China Academy of Building Research NZEBuilding

​The nearly zero energy building (NZEB) at the China Academy of Building Research (CABR) adhered to the design principle of "passive building, proactive optimization, economic and pragmatic". An ambitious annual energy consumption (...)


  • Published on 29 June 16
    by Tom Geelen|International
    Viewed 4715 times


  • Certification Scheme


    Location

    , 9233 Diekirch Luxembourg

    Technicals Features