Sport'Co sports complex in Beaucouzé

  • Project type : New Construction
  • Building Type : Indoor gymnasium, sports hall, stadium
  • Construction Year : 2019
  • Delivery year : 2019
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.
  • Net Floor Area : 4 174 m2
  • Construction/refurbishment cost : 6 000 000 €
  • Number of Seat : 500 Seat
  • Cost/m2 : 1 437 €/m2
  • Cost/Seat : 12 000 €/Seat


Moderated by : Hassan ABOUZID

Similar case studies

Gymnasium Castle Morange

Our architectural project stems directly from the program and our functional analysis. It revolves around the two main practices: sporting use and spectators. The readability of the organization in plan (simplicity and geometric rigor (...)

Gymnasium Patrick Cazal

The operation takes place within the heart of the family in PRU zone. This 35-hectare urban park dedicated to recreation in the heart of Saint-Denis, dotted with many amenities, contributes to the exchange and well-being of all Dionys (...)


  • Published on 13 May 19
    by Camille FAYET|France
    Viewed 1644 times
  • Proposed by :




  • Contest

    Green Solutions Awards 2019 - Buildings

    Health & Comfort
    Users' Choice


    Environment's respect
    Sobriety

    • Design based on the Négawatt scenario (sobriety, efficiency, renewable energies)
    • A building RT 2012 desired: a passive building proposed and soon positive energy
    • Heating at 12 ° C in sports halls
    • No hot water in the locker room sinks
    • Rainwater recovery for all Wcs
    • Establishment of a GTB to heat, illuminate and ventilate to just the necessary levels
    • Mechanical ventilation only when natural ventilation is not possible

    Efficiency

    • High performance envelope (27 cm LR)
    • High performance equipment:
    • Natural ventilation thanks to external air intake grilles controlled according to the indoor and outdoor temperatures (COLT system)
    • Double flow ventilation with an air sensor system for preheating the air in winter (Aérollagg system)
    • Intelligent ventilation control via a GTB with priority to natural ventilation
    • Natural light well SOLARSPOT
    • 3 air / water PACs that generate low temperature heating and DHW for changing rooms
    • Recovery of EP for sanitary
    • BEPOS level achieved with the rental of the roof for the installation of photovoltaic panels
    • Use of renewable energy: air, water and sun / light

    renewable

    • Preheating the fresh air of a DF unit with air solar collectors
    • Buildings designed for photovoltaic installations
    • Natural ventilation controlled

    Quality of life

    Winter thermal comfort:

    • Comfort temperature 12 ° C sports halls and 19 ° C elsewhere
    • Low temperature radiant ceilings
    • Double-flow ventilation (milk preheating by Aérollagg system)

    Thermal comfort between seasons and summer

    • Natural ventilation all-weather operation controlled via GTB (colt system)
    • Unloaded building discharge (colt system, free cooling)

    Visual comfort:

    • FLJ studies for all premises
    • Glazing polycarbonate glazing with anti-glare treatment
    • Sun protection minimizes direct radiation on all facades
    • Skylight in the locker room
    • Modulation of artificial lighting according to natural intake and practiced sport
    • Implementation of high quality LED luminaire to avoid glare

    Acoustic :

    • Integration of technical equipment in closed or protected premises
    • Technical premises adjacent to buffer rooms
    • Acoustic treatment in all spaces (walls, ceilings)

    Services :

    • Space of conviviality with a bar
    • Meeting room
    • Infirmary
    • Gym: party room

    Economic performance

    • High performance building for a zero energy bill (after photovoltaic installations)
    • Choice of local actors mainly for design and implementation

    Responsible management

    • Internal management at the MOE: CRR Architecture and CRR Engineering
    • Presentation of STD and FLJ calculations at MOA in APS and APD: decision support
    • Monitoring, performance management and maintenance via GTB

    Certification Scheme