BSolutions: Certified passive and BREEAM

  • Project type : New Construction
  • Building Type : Office building < 28m
  • Construction Year : 2011
  • Delivery year : 2013
  • Climate zone : [Cbc] Mild, dry winter, warm and wet summer.
  • Net Floor Area : 1 113 m2
  • Construction/refurbishment cost : 1 922 000 €
  • Number of Work station : 80 Work station
  • Cost/m2 : 1 727 €/m2
  • Cost/Work station : 24 025 €/Work station


Moderated by : C21 France La redaction

Similar case studies

Almelo City Hall

​As part of a larger plan to revitalise the city centre of Almelo, the newly built city hall is an example of sustainable construction and modern design. With sustainability as the cornerstone of its design, the building is currently (...)

Studio Bruno Stagno Architect

The building is located in a neighborhood of San José, Costa Rica, whose buildings date back to the second half of the 20th century.The vast majority of them are houses, but some of them have been transformed into shops and offices (...)

Kuggen. Ecopilot, energenious building automation system

​KabonaABKabona is a company which works with energenious energy building automation and the company’s head office is locatedin Borås, Sweden. Kabona was founded in 2001 and has long-standing and solidexperience, which has formed the (...)


  • Published on 21 March 16
    by Cédric Anbergen|Belgique
    Viewed 7529 times


  • Contest

    Green Solutions Awards 2017 - Buildings

    Energy & Temperate Climates
    Health & Comfort
    Smart Building
    Users' Choice
    Sustainable Construction Grand Prize



    Certification Scheme


    Location

    , 5032 Isnes - Gembloux Belgique

    Technicals Features