LVR Boarding school, Euskirchen

4047
Last modified by the author on 07/04/2021 - 10:28

New Construction

  • Building Type : School, college, university
  • Construction Year : 2018
  • Delivery year : 2018
  • Address 1 - street : Augenbroicher Straße 49 D - 53879 EUSKIRCHEN (NORDRHEIN-WESTFALEN), Deutschland
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.

  • Net Floor Area : 443 m2
  • Construction/refurbishment cost : 6 906 370 €
  • Number of Pupil : 8 Pupil
  • Cost/m2 : 15590 €/m2

Certifications :

  • Primary energy need
    80 kWhpe/m2.year
    (Calculation method : Other )
Energy consumption
Economical buildingBuilding
< 50A
A
51 à 90B
B
91 à 150C
C
151 à 230D
D
231 à 330E
E
331 à 450F
F
> 450G
G
Energy-intensive building

For the Landschaftsverband Rheinland (LVR), a total of four boarding school residential buildings for 8 pupils each with the special focus on "hearing and communication" were built. The single-storey buildings without basements are built in partially prefabricated timber frame construction. Each of the four residential buildings has four single and two double rooms. Ecological, resource-saving building materials and energy-saving construction methods were the basis for planning and execution. Both the new boarding school buildings and the associated outdoor area with its diverse play areas in the open spaces are barrier-free. For capacity reasons, two of the existing group houses, which were gradually dismantled until the completion of the entire construction project, had to remain in operation. Thus, the new boarding school buildings were realised in two main construction phases during ongoing operation.

See more details about this project

 https://passivehouse-database.org/index.php?lang=en#d_6552

Data reliability

Assessor

Photo credit

Marc Mevißen

Contractor

Construction Manager

    Siemons & Hermann

Stakeholders

    Others

    Schwinn Ingenieure


    Others

    Ingenieurbüro Knabben + Korbitza

Owner approach of sustainability

-Ecological, resource-saving building materials and energy-saving construction method

-Green flat roofs

Architectural description

On the property at Augenbroicherstrasse 49, 48 children were accommodated in 6 existing bungalows from the 1960s. Due to serious structural defects in the existing buildings, the LVR decided to demolish the old boarding school bungalows and replace them with new buildings. The four passive house boarding school residential buildings were built using a partially prefabricated timber frame construction and each have room for 8 residents in four single and two double rooms. Ecological, resource-saving building materials and energy-saving construction methods were the basis for planning and execution. Wood, a renewable and thus resource-saving main building material, was chosen. In addition, only ecologically safe and recyclable building materials were used. Both the new boarding school buildings and the associated outdoor area with its diverse play areas in the open spaces are barrier-free. For capacity reasons, two of the existing group houses, which were gradually dismantled until the completion of the entire construction project, had to remain in operation. Thus, the new boarding school buildings were realised in two main construction phases during ongoing operation.

Energy consumption

  • 80,00 kWhpe/m2.year
  • 95,00 kWhpe/m2.year
  • Other

    Heating demand 14 kWh / (m2a) calculated according to PHPPPE demand (non-renewable primary energy) 80 kWh / (m2a) for heating, hot water, auxiliary and household electricity calculated according to PHPPPER demand (renewable primary energy) 83 kWh / (m2a) for heating, Hot water, auxiliary and household electricity calculated according to PHPP

Envelope performance

  • 0,13 W.m-2.K-1
  • External wall timber frame construction: Fermacell GFP 10mm insulation WLG 040 60mmFermacell GFP 13mm OSB board 18mmFachdämmung WLG 040 280mmDWD board 16mmU-value = 0.133 W / (m2K) basement ceiling / floor slab Floor slab: flooring anhydrite screed on system slab WLG 300mm -Value = 0.103 W / (m2K) roof flat roof: system structure green roof with sealing 160mm insulation 280mm cross-laminated timber ceiling 140mmU-value = 0.081 W / (m²K) monopitch roof: metal cladding insulation WLG 032 430mm cross-laminated timber ceiling 120mmU-value = 0.081 W / (m²K) U-value = 0.081 W / (m²K) U-value = 0.081 W / (m²K) U-value = 0.081 W / (m²K) / (m2K) Window frame wood-aluminum window IV 78 passive, IV 78 passive wood-aluminum window Uf value = 0.72 W / (m²K) U w value = 0.85 W / (m2K) Glazing triple thermal insulation glazing U g- Value = 0.6 W / (m2K) g value = 53% entrance door wood-aluminum-glass system U d-value = 0.85 W / (m2K)

  • 0,48

Systems

    • Geothermal heat pump
    • Gas boiler
    • Solar cooling
    • No cooling system
    • compensated Air Handling Unit
    • Double flow heat exchanger
    • Heat Pump on geothermal probes

    PER demand (renewable primary energy): 83 kWh / (m2a) on heating system, hot water, household electricity and auxiliary electricity, calculated according to PHPP

Construction and exploitation costs

  • 10 374 617

Reasons for participating in the competition(s)

On the property at Augenbroicherstrasse 49, 48 children were accommodated in 6 existing bungalows from the 1960s. Due to serious structural defects in the existing buildings, the LVR decided to demolish the old boarding school bungalows and replace them with new buildings. The four passive house boarding school residential buildings were built using a partially prefabricated timber frame construction and each have room for 8 residents in four single and two double rooms. Ecological, resource-saving building materials and energy-saving construction methods were the basis for planning and execution. Wood, a renewable and thus resource-saving main building material, was chosen. In addition, only ecologically safe and recyclable building materials were used. Both the new boarding school buildings and the associated outdoor area with its diverse play areas in the open spaces are barrier-free. For capacity reasons, two of the existing group houses, which were gradually dismantled until the completion of the entire construction project, had to remain in operation. Thus, the new boarding school buildings were realised in two main construction phases during ongoing operation.

 

Building candidate in the category

Alle Kategorien

Alle Kategorien

Green Solutions Awards 2020-2021 / Deutschland
PDF
 Boarding school LVR timber construction green building school construction

Share :
Author of the page

Marc Mevißen


Other case studies

More

Contest

Green Solutions Awards 2020-2021 / Deutschland