• Building Type : Factories
  • Construction Year :
  • Delivery year : 2023
  • Address 1 - street : 2 rue du Cardo 62073 BAILLEUL-SIR-BERTHOULT, France
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.

  • Net Floor Area : 1 435 m2
  • Construction/refurbishment cost : 2 800 000 €
  • Number of Installed Kw : 3 Installed Kw
  • Cost/m2 : 1951.22 €/m2
  • Primary energy need
    kWhep/m2.an
    (Calculation method : )
Energy consumption
Economical buildingBuilding
< 50A
A
51 à 90B
B
91 à 150C
C
151 à 230D
D
231 à 330E
E
331 à 450F
F
> 450G
G
Energy-intensive building

The LFB (French Fractionation and Biotechnology Laboratory) is building a “new generation” plant in the Actiparc area near Arras to produce plasma-based medicines in France for the whole world, used as treatments for many diseases.

As part of the construction of the site, LFB wanted to dedicate a building dedicated to the management of its waste and other by-products from production. The recovery unit makes it possible to transform an infectious by-product from the production building into a source of recycled raw materials made up of unmarked plastic flakes.

In order to extend its circular economy approach beyond the actual function of the building, LFB wanted to design a building with low environmental impact, under the prism of the circular economy.

Environmental approach: matter and energy

The project pays particular attention to the construction materials considered. It promotes biosourced materials, from recycling, reuse and local channels:

  • The structure of the building is entirely in Douglas wood frame from national sectors;
  • The envelope is made up of wooden frame walls with straw filling;
  • The facades are made up of Eternit panels from the end of stocks intended for the recycling centre;
  • The waterproofing of the light-coloured cover to prevent overheating is made of recycled and recyclable materials;
  • The concrete slab is made up of 50% recycled aggregates from a demolition site less than 40km away;
  • The insulation of the partitions is made of métisse manufactured less than 40km

With a view to saving material in the short and medium term, all the construction materials are carefully implemented so as to remain raw: quartz concrete paving, exposed breeze block walls for the storage rooms, raw Fermacell panel on the interior facade walls, etc.

In order to reduce the energy necessary for its operation, the project uses the resources available on the site, resulting from the activity of the factory. Heating needs are recovered from the heat generated by the recovery process within the building. The supply of the machines necessary for the recovery process uses the compressed air network produced on site.

Bioclimatic approach

The design of the building promotes bioclimatic systems by invoking natural and passive resources to meet thermal, hygrometric and air renewal needs.

Located on the plains of Artois largely exposed to the winds, the building benefits from a natural ventilation system allowing natural sweeping of the process, a source of heat. The grids ofventilation located in the lower part of the South-West facade, exposed to the prevailing winds, allow the air to circulate in the heart of the building up to the chimney which, under the draft effect, evacuates the hot air in the upper part . Mechanical ventilation is provided in addition in case of high temperatures.

The ventilation system is regulated via interior temperature sensors and a weather station on the roof.

Like industrial sheds, the volume of the chimney also allows a supply of zenithal light on the North side to avoid overheating.

Rainwater collected from the roofs is stored in a tank to be used for building maintenance and washing the bins that transported the by-products.

Volumetric principles

The building is composed of a compact primary envelope hosting the by-product recovery process. Its French glued laminated Douglas wood frame structure gives it large spans to make room for a large open volume. In order to limit energy expenditure and improve user comfort, the building envelope is fully insulated by wooden frame walls with straw filling.

A second volume wraps around this envelope to form a canopy, necessary for the protection of storage and deliveries.

Principles of facades

The cladding envisaged for the facade was the subject of a partnership with the supplier Eternit to identify and recover end-of-series stocks, taken out of the market and intended for the waste disposal center in the near future.

The design of the facades was therefore done in the opposite way to the customs of the prescribers that we are, in the sense that the composition of the colors and the layout was thought out from the available stocks. The layout of the facades favors small modules at the foot of the building to facilitate their replacement in the event of damage over time.

Building users opinion

This building is efficient, scalable and a concrete action of the company's CSR approach.

If you had to do it again?

For the building, we did not succeed in using poplar construction wood in the local sector, despite discussions with suppliers upstream of the consultation of companies, no official reservation of stocks has been initiated by the Control of work which feared the additional cost during the call for tenders. Finally, the cost was not higher than the French Douglas sector (New Aquitaine region), but the delivery time announced by the supplier caused a delay on the site of 6 months. The construction wood therefore comes from the New Aquitaine region.

Photo credit

BLAU

Contractor

Construction Manager

Stakeholders

    Assistance to the Contracting Authority

    NEO ECO

    Maude SOUBEIRAN, msoubeiran[a]neo-eco.fr

     https://www.neo-eco.fr/

    AMO circular economy


    Structures calculist

    INGEBOIS

    Laurent LEPAUL, laurent.lepaul[a]ingebois.com

     https://ingebois.com/

    Studies of wooden structure and wooden facades



    Thermal consultancy agency

    TWI ingénierie

    Julien FROGER, julien.froger[a]tw-ingenierie.com

     https://www.tw-ingenierie.fr/

    Fluid studies, plumbing, thermal


    Other consultancy agency

    PROJET

    Laurent Versalie

    Electrical studies


    Company

    SATELEC

    Richard Dendauw

    Electrical studies


    Company

    SNPC

    Florimond LEPOUTRE

    Road studies, networks

Contracting method

Lump-sum turnkey

Type of market

Not applicable

Allocation of works contracts

Separate batches

Energy consumption

    Industrial building not subject to thermal regulations

Envelope performance

    Facade in wooden boxes filled with straw 36cm. Coverage by waterproofing, white membrane implemented to prevent overheating in summer.

More information

No feedback yet, building not currently in operation. The industrial process machines will only be installed in 2024.

Systems

    • Electric radiator
    • Other hot water system
    • No cooling system
    • Natural ventilation
    • No renewable energy systems

    The space in the hall hosting the industrial process has no means of heating. The process releasing heat, it will heat the hall in winter while in summer the space will be cooled by a natural ventilation system. Indeed, air intake grilles in the lower part of the facade exposed to the prevailing winds allow the air to circulate in the hall until it is extracted via grilles positioned in the chimney (the shed). Only staff premises are heated by electric heaters (office, break room, changing rooms). The need for domestic hot water production and ventilation for the changing rooms and the break room is provided by a thermodynamic tank.

    Rainwater harvesting

Urban environment

    Insertion in an industrial site within an Activity Zone in creation, no existing context.

Product

    Low carbon concrete slab

    GCC / PLACEO / EQIOM

    Second œuvre / Revêtements de sol 

    GCC produced with PLACEO as a subcontractor the interior paving composed of 50% recycled aggregates and the exterior paving composed of 30% recycled aggregates.

    The formulations have been developed in partnership with EQIOM and have been certified by the control office. In particular, durability tests were carried out.

Construction and exploitation costs

  • 300 000
  • 2 800 000
  • 360 000

Circular economy strategy

    Preliminary design studies

    • Maximization of quantities on targeted products

    We have created a partnership with Equitone to recover end-of-series cladding panels withdrawn from the market and sent to recycling channels.

    Integration of the reuse specifically in the special technical specifications of the concerned batches

    Yes

    Stock constituted and reserved with the supplier, obligation of the company to go through this supplier and this specific stock.

    No

Reuse : same function or different function

    • Facades

    Equitone cladding:

    • 2,300 m²
    • End of series of Equitone supplier not marketed
    • Reuse in facade cladding

    The end-of-series stocks constituted a database which required design work contrary to usual: we designed the layout and the colorimetry of the facade according to the existing deposit. The implementation on site remains classic, identical to the products marketed.

Logistics

    No

    • No problem of storage, supply correlated to the progress of the works

Insurance

    Yes

    No specific mission. We discussed with him during the study phase, the material having not been laid beforehand on another operation, its implementation did not require any specific process.

    No

    No

    SWISS

    Yes

    Yes, on the reuse of the cladding panels as well as on the integration of recycled aggregates up to 50% in the concrete of the interior slab and 30% for the exterior slab. The choice of straw insulation was also discussed, particularly with regard to the fire constraints linked to the building to respect the REI60 on part of the facades. Insurers were more favorable to the use of straw rather than wood fibre, as straw gives off less smoke in the event of a fire. A Fermacell partition under PV was implemented on the interior facade walls in order to comply with fire constraints.

Environmental assessment

Economic assessment

  • 203 000
  • Yes

    • Others

    Materials reserved during studies with supplier but not purchased. Direct purchase with the construction company.

    A comparative economic study was carried out in the PRO phase to measure the financial gap between the construction of a low-carbon industrial building and a "standard" building in industry (replacement of the wooden frame with a metal frame, replacement of the floors wood with concrete floors, replacement of wood / straw / Equitone facades with metal facades with mineral insulation, removal of bay windows with compensation for artificial lighting and removal of rainwater recovery). The difference measured is 29.72%. However, the return on investment has not been calculated.

    The cost of end-of-series panels was lower than the cost of conventional panels on the market. The price had been negotiated and blocked with the supplier during the studies. The price for the supply of reused panels, excluding installation, had been negotiated with the supplier at approximately €35/m2.

Communication

    Yes

    Presentations at conferences (Presentation at the Arras Academy of Architecture during an intervention by La Frugalité Heureuse et Créative Hauts-de-France; Presentation at a Building Lab round table: Presentation at the 8th meetings of Straw Wood Construction, etc.).

    Yes

Circular design

    The choice of construction materials and their implementation have been studied to remain raw and avoid the addition of finishing materials. This approach aims to limit the consumption of materials, both from the construction stage but also over a longer period of time with regard to maintenance and renewal of finishes.

    • Use of energy produced for the entire LFB site (example: use of compressed air produced for the entire site for our building);
    • Industrial process recovering infectious risk waste from LFB production which, until now, was sent to a treatment center;
    • Use of natural resources to meet the energy needs of the building (natural ventilation, recovery of rainwater for the industrial process, favoring the contribution of natural light, no heating for the main hall which will be naturally heated by the energy released by the machines, etc.);
    • Pooling of living bases to all buildings under construction on the LFB site.

    The building provides sufficient space to double the industrial process in the future. Expectations for adiabatic ventilation devices are provided to respond to greater overheating thereafter.

    • Recyclable clear waterproofing membrane;
    • Use of recycled cotton insulation for the interior walls (Metisse);
    • Concrete composed of recycled aggregates (50% for the interior slab and 30% for the exterior slab). Tests were carried out by test specimen during studies by Neo Eco in partnership with Eqiom in order to develop the formula of the concretes used.

Additional information (PDF documents)

Reasons for participating in the competition(s)

We are competing in the Green Solutions Awards 2022-2023 competition and the Circular Buildings Trophies because they convey in all respects the actions that we have carried out on the recovery unit with the FBL.

The design of the building followed the virtuous approach of the Client to create a building that recycles the waste resulting from its production, it is therefore natural that the design choices fell on the principles of the circular economy and the bioclimatic architecture. The building was designed to consume little (example of an efficient envelope insulated with straw) and the energy necessary for its operation comes mainly from natural resources (wind, rain, sun). The choice of materials has been oriented towards recycling, reuse or bio-sourced channels, they are locally sourced as much as possible. The fire regulatory aspect (some exterior facades must comply with REI60 resistance) has been studied to allow the use of straw on the facade. The will of the Project Management and Project Management team has focused on a low-carbon demonstrator industrial building, which participates in the development of local sectors and which constitutes feedback for other manufacturers who would like to take the same approach. In addition, the Contracting Authority wishes to organize regular visits to the building in operation in order to raise awareness among the general public, manufacturers and building specialists.

Building candidate in the category

Maîtres d'ouvrage privés - bâtiments tertiaires

Maîtres d'ouvrage privés - bâtiments tertiaires

Trophées Bâtiments Circulaires 2023
PDF
 bioclimatism reuse recycling ecomaterials wood renewable energies frugality Green Solutions Awards Green Solutions Awards 2022 2023

Share :
Author of the page

Amandine Martin

Architecte


Other case studies

More

Contest

Trophées Bâtiments Circulaires 2023