Alexandre Dumas Residence

Renovation

  • Building Type : Collective housing < 50m
  • Construction Year : 1965
  • Delivery year : 2021
  • Address 1 - street : 4 rue Alexandre Dumas 78230 LE PECQ, France
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.

  • Net Floor Area : 7 275 m2
  • Construction/refurbishment cost : 1 094 665 €
  • Cost/m2 : 150.47 €/m2
  • Primary energy need :
    127 kWhep/m2.an
    (Calculation method : RT existant )
Energy consumption
Economical buildingBuilding
< 50A
A
51 à 90B
B
91 à 150C
C
151 à 230D
D
231 à 330E
E
331 à 450F
F
> 450G
G
Energy-intensive building

The condominium voted for a high-performance energy renovation project during the general meeting of June 2019 relating to:

  • the renovation with thermal insulation from the outside of all the facade walls ;
  • replacing the boiler with an efficient gas condensing boiler ;
  • installation of thermostatic valves.

Some co-owners also took advantage of this project to replace their original joinery.

Photo credit

Citymetry

Contractor

    Résidence Alexandre Dumas

Construction Manager

    EMMANUEL DE BENOIST

Stakeholders

    Assistance to the Contracting Authority

    CITEMETRIE

    copro78[a]citemetrie.fr

     www.citemetrie.fr

    AMO Financial Engineering.


    Company

    GESTEN

    Boiler room


    Company

    SOCATEB

    Refacing with ITE

Energy consumption

  • 127,00 kWhep/m2.an
  • 193,00 kWhep/m2.an
  • RT existant

  • 193,00 kWhep/m2.an

Systems

    • Condensing gas boiler
    • Gas boiler
    • No cooling system
    • Natural ventilation
    • No renewable energy systems

Urban environment

    The condominium is located in the Ermitage district in Le Pecq.

Construction and exploitation costs

  • 20 000
  • 1 114 665
  • 298 461
  • Aid details:
    Co-ownership filed under the HMS program:
    - Anah grants: €239,760.94
    - CD78 grants: €45,200
    - Aid from CA SGBS: €13,500
    => That is a total of subsidies of €298,460.94 for a package of works amounting to €1,094,665.96 excluding tax
    The average share is €18,026.54.

Reasons for participating in the competition(s)

Following the vote on the works in June 2019, the condominium started the works at the beginning of 2020.

The construction site had to be interrupted following the health crisis for several weeks.

Despite the Covid-19 epidemic, the project was still able to see the light of day and the work was successfully completed.

Thanks to this project, we were able to observe a marked improvement in comfort with the co-owners.

The costs relating to the production of heat have also been considerably reduced, in particular due to the replacement of the old dilapidated boiler by a more efficient and less energy-consuming model.

The condominium is now continuing its energy renovation and has recently undertaken the insulation of the roof terraces.

Trophées des Copros des Yvelines
PDF

 Trophies of the Copros des Yvelines
 renovation
 energy savings
 ITE
 better living
 boiler room
 performance
 building
 renovation
 energy
 housing