Extracurricular Madeleine

2099
Last modified by the author on 18/10/2022 - 11:14

New Construction

  • Building Type : School, college, university
  • Construction Year : 2019
  • Delivery year : 2019
  • Address 1 - street : 8 Bld Porte Madelaine 45150 JARGEAU, France
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.

  • Net Floor Area : 364 m2
  • Construction/refurbishment cost : 891 196 €
  • Cost/m2 : 2448.34 €/m2

Certifications :

  • Primary energy need
    61.4 kWhep/m2.an
    (Calculation method : RT 2012 )
Energy consumption
Economical buildingBuilding
< 50A
A
51 à 90B
B
91 à 150C
C
151 à 230D
D
231 à 330E
E
331 à 450F
F
> 450G
G
Energy-intensive building

The new building is built in a built environment with its own history and functioning. We wanted to establish consistency between the buildings, enhance the existing site through the controlled integration of the new construction . We organized all the buildings around the courtyard. The latter is a protected space, conducive to exchanges and which makes it possible to articulate the different spaces (courtyard, existing buildings, sanitary facilities), to strengthen the links with the existing biodiversity space and to accentuate the connection with the sports centre.

The school group's boiler room, sized for all of the school's existing buildings, was renovated in 2016. Rather than resizing this installation and providing buried networks to bring the gas to the new building, we proposed to carry out a bioclimatic building which would make it possible to get rid of “gas” energy and which would reach the passive thermal optimum. This also keeps running costs to a minimum. A pedagogical approach has been initiated with students to make them aware of the environment and site visits have been organized with professionals.

Environmental approach

The entire construction is made of wooden frame walls including straw insulation , cladding made of rough sawn Douglas fir planks with joint cover. The exterior joinery is made of wood. In order to promote the retention of rainwater and thermal comfort, a green roof terrace , also insulated with straw, covers the entire new building and overflows to form the courtyard and the awning. This roof is designed as a “green” footbridge which ensures continuity between the Loire and the biodiversity area. Finally, the floors are made of NORA natural rubber and the paints benefit from the European Ecolabel.

See more details about this project

 https://www.envirobatcentre.com/centre-de-ressources/les-projets/fiche-projet/periscolaire-madeleine

Photo credit

BHPR

Contractor

    Mairie de Jargeau

Construction Manager

    BHPR Architectes

Energy consumption

  • 61,40 kWhep/m2.an
  • 73,60 kWhep/m2.an
  • RT 2012

Systems

    • No heating system
    • Individual electric boiler
    • No cooling system
    • Double flow heat exchanger
    • No renewable energy systems

Urban environment

    The new building is built in a built environment with its own history and functioning. We wanted to establish consistency between the buildings, enhance the existing site through the controlled integration of the new construction. We organized all the buildings around the courtyard. It is a protected space, conducive to exchanges and makes it possible to articulate the different spaces (courtyard, existing buildings, sanitary facilities), to strengthen the links with the existing biodiversity space and to accentuate the link with the sports centre.

Product

    Natural rubber floors

    NORA

     https://www.nora.com/france/fr

    Second œuvre / Revêtements de sol 

    nora® floor coverings are made from high-quality natural and industrial rubbers. They are mixed with minerals from natural sources and other compounds, including environmentally friendly color pigments, then cut into blanks, pressed and vulcanized under the effect of heat and high pressure. Thanks to the flexibility of the material, rubber flooring does not require any plasticizer. The nora cleanguard® cross-linking then carried out in the factory creates a dense and closed surface, without the application of a protective layer. This is why our rubber floor coverings will never need surface protection (varnish, wax, metallization): even after many years of use, their appearance remains new.

Construction and exploitation costs

  • 891 196

Reasons for participating in the competition(s)

  • Use of biosourced materials: Douglas fir wood and straw insulation;
  • Passive building thanks to a bioclimatic design;
  • A green roof for summer comfort, thermal efficiency and biodiversity;
  • A new construction integrated into the existing site.

Building candidate in the category

Prix du public

Prix du public

Green Solutions Awards 2022-2023 / France
PDF
 Green Solutions Awards Green Solutions Awards 2022 2023 concours

Share :
Author of the page

Gwennaël Liger


Other case studies

More

Contest

Green Solutions Awards 2022-2023 / France