Idrija mercury smelting plant

Extension + refurbishment

  • Building Type : Museum
  • Construction Year : 2014
  • Delivery year : 2017
  • Address 1 - street : Arkova ulica 50 5280 IDRIJA, Slovenia
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.

  • Construction/refurbishment cost : 2 300 000 €
  • Cost/m2 : INF €/m2
  • Primary energy need
    kWhpe/m2.year
    (Calculation method : )
Energy consumption
Economical buildingBuilding
< 50A
A
51 à 90B
B
91 à 150C
C
151 à 230D
D
231 à 330E
E
331 à 450F
F
> 450G
G
Energy-intensive building

The diverse and unique industrial and technical heritage of Idrija’s 500-year-old mining history was inscribed on UNESCO World Heritage List in 2012. One of the crucial parts of the mercury mine was the smelting plant, which stopped operating in 1995. Its renovation and renewal was a significant challenge in terms of financing and expertise. The energy renovation of the building was carried out in accordance with the possibilities and specifications of the building, which belongs to the technical cultural heritage. The project comprised the reconstruction and extension of the existing ore separation facility and construction of a new building intended for reception of visitors and hosting a permanent exhibition 'From ore to mercury drops'. Two investment phases were planned - the first one is finished, the second one will focus on the furnace, extraction and packaging of mercury in cylinders. In 2020 the refurbushed Idrija mercury smelting plant won the 2nd prize of the ‘Destination of Sustainable Cultural Tourism’ award under category of industrial heritage.

 https://idrija.si/files/other/news/54/599691.pdf
 https://www.hiberatlas.com/sl/idrija-mercury-smelting-plant--2-72.html

Photo credit

Posoški razvojni center
R. Bizjak

Contractor

Construction Manager

Stakeholders

    Others

    Institute for the protection of cultural heritage of Slovenia

    Delpinova 16, 5000 Nova Gorica, tajnistvo.ng[a]zvkds.si

     https://www.zvkds.si/en

Contracting method

Other methods

Envelope performance

    In the reconstructed part of the building, there are concrete frame structures with masonry walls in between. All walls, except in the basement, were additionally thermally insulated with EPS panels on the inside of the building, and a cement spray performed over them.
    The window openings remained the same, windows were replaced with ALU windows with double-layer thermopane glazing.
    The roof is made of reinforced concrete beams, to which a wooden substructure is attached. The asbestos roofing has been replaced with a new suitable corrugated roofing. The roof is thermally insulated with soft mineral wool 25 cm thick, and the inside is lined with OSB panels, which are treated with cement spray over galvanized welded metal mesh.
    Existing window U-value Glass [W/m2K]: 0,0
    New window U-value Glass[W/m2K]: 1,1

Systems

    • Wood boiler
    • Wood boiler
    • Wood boiler

Urban environment

    The building is situated within the industrial area of Idrija. Part of the larger area was sold to another company after the mine stopped its operations. This changed significantly the former visual identity of the town.

Construction and exploitation costs

  • 2 300 000
  • 2 000 000
  • The CUDHg Idrija successfully applied to a call for proposals to co-finance the project "Idrija – smelting plant area, of the Idrija mercury mine – 1st phase of reconstruction" under the EEA Financial Mechanism Programme 2009-2014 – B.3. Cultural Heritage, for the amount of EUR 2 million.

Reasons for participating in the competition(s)

The goal of retrofitting was to preserve the endangered cultural monument and enrich it with new content, enhance its modernity and attractiveness, revive its heritage with educational content, raise awareness of the importance of preserving cultural heritage, and enhance tourism opportunities in the area.

Building candidate in the category

Low Carbon

Low Carbon

Green Solutions Awards 2020-2021
PDF
 Gea Consult Center za upravljanje z dediščino živega srebra buildings refurbishment heritage hiberatlas UNESCO energy

Share :
Author of the page

Jana Podgornik


Other case studies

More

Contest

Green Solutions Awards 2020-2021