"Murs à pêches" Pool

  • Project type : New Construction
  • Building Type : Swimming pool
  • Construction Year : 2017
  • Delivery year : 2017
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.
  • Net Floor Area : 3 800 m2
  • Construction/refurbishment cost : 16 500 000 €
  • Number of Shower/day : 1 125 Shower/day
  • Cost/m2 : 4 342 €/m2
  • Cost/Shower/day : 14 667 €/Shower/day


Moderated by : Guillaume Aichelmann

Similar case studies

London Aquatic Center

Abstract ‘Legacy’ is the concept that underlies the sustainability agenda of the London 2012 Olympic and Paralympic Games, embracing temporary infrastructure and venues to leave behind a vibrant, productive community with world-class (...)

Aquatic Center Champsaur

This aquatic center was created from the old village pool which only worked in the summer: it is now ope all year long as it is roofed now. To reduce energy consumptions, the principles of bioclimatic architecture have been met:passiv (...)

SEMI OLYMPIC SWIMMING POOL COVERED IN SIDI YOUSSEF BEN ALI

The semi-Olympic swimming pool covered in Sidi Youssef Ben Ali in Marrakesh, swimming pool of last generation, it was coordinated and piloted by the regional direction of the ministry of youth and sport of a superficiecouverte of (...)


  • Published on 11 May 17
    by Valérie Baudot|France
    Viewed 5540 times


  • Contest

    Green Solutions Awards 2018 - Buildings

    Energy & Temperate Climates
    Users' Choice


    1st aquatic center with spaces in passive construction (energy neutral), construction in wood frame labeled PEFC, centralized technical management, reinforced insulation, recyclable materials, heat pump, wood boiler, solar thermal collectors, green roof, hydrolise salt, comfort ventilation, high effi ciency heat recovery, a low-nuisance ...

    Natural outdoor swimming without chlorine.

    Total primary energy = 79% renewable energy.


    Location

    rue Maurice Bouchor , 93100 MONTREUIL France

    Technicals Features