LONGUEAU E=0

  • Project type : Renovation
  • Building Type : Isolated or semi-detached house
  • Construction Year : 1965
  • Delivery year : 2018
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.
  • Net Floor Area : 960 m2
  • Construction/refurbishment cost : 1 483 703 €
  • Number of Dwelling : 12 Dwelling


Moderated by : Hassan ABOUZID

Similar case studies

Butterfly House

This is an energy efficient house that was built by the University of Ubonratchathani in 2005 as part of a research project funded by the Ministry of Energy of Thailand. 2-storey house with 2 bedrooms on the second floor and living (...)

House at Carrickmines

The Project was to construct a c.200sqm single storey detached 3/4-bedroom house in Carrickmines.  We started on site in mid July 2018 and the house was PC certified in February 2019.Sustainability  The site is in a beautiful serene (...)

First passive house in Brazil

First construction in Brazil built according to the international Passive House standard and financed by the Bundesministerium für Bildung und Forschung – BMBF (German ministry of Education and Research) in partnership with SENAI (...)


  • Published on 07 June 19
    by VIRGINIE CARCHIDI|France
    Viewed 754 times


  • Contest

    Green Solutions Awards 2019 - Buildings

    Energy & Temperate Climates
    Users' Choice


    The energy renovation of existing buildings is a major issue in the coming years, particularly the individual park. The experience of this project in the context of social housing could eventually reduce the costs of thermal rehabilitation of the individual park but also collective, by a massification of the concept and therefore a reduction in manufacturing costs (including facades).


    Certification Scheme


    Location

    175-189 rue du Maréchal Joffre , 80330 LONGUEAU France

    Technicals Features