TADI Office Complex – Building B

  • Project type : New Construction
  • Building Type : High office tower > 28m
  • Construction Year : 2014
  • Delivery year : 2015
  • Climate zone :
  • Net Floor Area : 20 560 m2
  • Construction/refurbishment cost : 202 000 000 ¥
  • Number of Work station : 930 Work station
  • Cost/m2 : 9 825 ¥/ m 2
  • Cost/Work station : 217 204 ¥/Work station


Moderated by : Maolin Liu

Similar case studies

Glorieta Insurgentes Tower

The Glorieta Insurgentes Tower is nominated for Green Solutions Awards because the conception of the project includes comfort, functionality, sustainability and energy efficiency with LEED Platinum Certification, transit oriented deve (...)

EAN Technology Headquarters

EAN Technology is Korea’s leading architectural engineering and consulting firm specializing in assessing and improving various environmental qualities of the built environment.  In 2016, EAN acquired an old office building that was (...)

CRYSTAL TOWER Business Center

Featuring modern, sophisticated and elegant architectural design and introducing the double skin glass façade - the first in Romania - CRYSTAL TOWER is a new landmark in Bucharest. With high architectural and technological standards (...)


  • Published on 17 June 19
    by lisha he|中国
    Viewed 278 times


  • Contest

    Green Solutions Awards 2019 - Buildings

    Low Carbon
    Health & Comfort


    1.In terms of user welfare, the Project upholds the design philosophy of “People oriented”, and provides a comfortable, pleasant, and relaxed working environment full of dynamic fashion for employees in consideration of the practical demands of architects, with an aim to improve the health level of the users at the physiological, psychological, and social levels; 

    2. As to environmental impact, the Project focuses on ecology protection and bio-friendliness: a number of “sponge city” technologies and measures are adopted to utilize and restore the ecological resources on the existing ground; the trees in the surrounding area are bypassed and protected, which not only preserves the existing 50+ tall trees, but also hands down the 67 years of historical memory of and affections for the Tianjin Architecture Design Institute. After the Project is completed, the trees will make a pleasant shade and the water will flow with murmur in the Institute, providing a beautiful and pleasing work environment for the employees with harmonious coexistence of human and nature; From green construction to green operation, during the whole process of the constructing and use of the Project, focus has been put on energy saving and consumption reduction, and the whole lifecycle carbon emission of the buildings is only about 48.8 kg CO2/m2/year;

    3. In terms of economic effectiveness, the Project has reasonable cost, with incremental cost per unit area of CNY 130.5/m2 and energy consumption per unit area in the operation stage of 53.67 Kwh/m2/year, showing significant energy-saving effect. The pay-back period of investment on green building technologies and measures is about 5 years, indicating remarkable economic effectiveness;

    4. As for technology application, all the healthy and green technologies and measures planned in the design stage of the Project have been implemented, and the green operation and maintenance platform designed and developed independently by our institute is used for the real-time monitoring of the indoor environment and various equipment, which is carefully maintained and managed by a professional operation and maintenance team, in order to ensure the continuous optimization during the process of technology application and operation and to realize healthy and green operation;

    5. In terms of feasibility, this Project is a representative practice of green technology in urban organic renewal and an active exploration in the aspects of ecological environment, spatial environment, cultural environment, and health management, which has reduced 80% of operation cost compared with similar projects and could provide reference for similar projects. During the urban construction process converting from incremental development to stock upgrading in China, the sustainable design philosophy and green and healthy building-integrated technologies of the Project are of great value for popularization. 


    Certification Scheme


    Location

    河西区气象台路95号 , 300074 天津 中国

    Technicals Features