LOUISE 120
Renovation
- Building Type : Office building < 28m
- Construction Year : 2010
- Delivery year : 2012
- Address 1 - street : Avenue Lousie, 120 1050 IXELLES, Belgique
- Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.
- Net Floor Area : 2 948 m2
- Construction/refurbishment cost : 3 080 000 €
- Number of Work station : 344 Work station
- Cost/m2 : 1044.78 €/m2
-
Primary energy need
58 kWhep/m2.an
(Calculation method : PEB - Bxl )
Data reliability
3rd part certified
Stakeholders
Contractor
ARIUM
J. Claude-Bouilly ; [email protected]
Designer
A2M sc sprl
Sebastian Moreno Vacca ; [email protected]
http://www.a2m.beOther consultancy agency
CES
F. Bayot ; [email protected]
Construction company
DEMOCO
Structures calculist
AUREA (AC)
V. Thimistere ; [email protected]
Environmental consultancy
IMTECH
M. De Viron Huybrechts ; [email protected]
Designer
Moreno architecture
Ste. Moreno ; [email protected]
Contracting method
Other methods
Energy consumption
- 58,00 kWhep/m2.an
- 250,00 kWhep/m2.an
- 31,90 kWhef/m2.an
- 350,00 kWhep/m2.an
Envelope performance
- 0,80 W.m-2.K-1
- 4,84
- 0,60
Systems
- Condensing gas boiler
- No domestic hot water system
- Others
- VAV Syst. (Variable Air Volume system)
- Nocturnal Over ventilation
- Double flow heat exchanger
- No renewable energy systems
Urban environment
- 841,20 m2
- 100,00 %
Product

GEA
-
http://www.gea.comGénie climatique, électricité / Ventilation, rafraîchissement
Construction and exploitation costs
- 3 080 000 €
Comfort
GHG emissions
- 15,64 KgCO2/m2/an