Wastewater Treatment Plant with Direct Potable Reusable Water

5119
Last modified by the author on 20/06/2019 - 16:38
  • Year of commitment : 2018
  • Address 1 - street : UN-CAMP KIDAL MALI , Other countries
  • Water cycle : Used water recycling
  • Circular economy and waste management : Reuse
    • Label/Certification :
      • HQE Infrastructures

  • 200 000 €
  • Builder
    The MasterMind Company
  • Manager / Dealer
    J.H. Wissink

We've engineered, built and serviced our Water Treatment Plant at the UN-camp in Mali. This is the first ever build Treatment Plant at this size. With this project we answer to the essence of our company; saving a source of the earth: water!

In the middle of the desert at the military camp of the United Nations’ Peace Mission in Mali Han Wissink of the MasterMind Company has managed to build a compact water- treatment installation to turn wastewater directly into drinking water. It has not been not a simple task, but mainly thanks to sophisticated online monitoring, including the detection of coliform bacteria, the camp is now abstracting only 35% groundwater per day which is a reduction of 65%. If it were up to Wissink, it would be down to 25%. The MasterMind water treatment plant at the UN camp in Mali is equipped with an online BACTcontrol sensor made by their partner in the Netherlands.


TMMC's wastewater treatment plant (WWTP) treats waste water (black water) in 2 steps:

  • into indirect reusable water that can be infiltrated in the ground (water suitable for the production of drinking water) without solution.
  • into DIRECT POTABLE REUSABLE WATER that can be used as an extra well for a Water Treatment Plant

This system reduces the intake of fresh ground water with 70-75%

Residu's of both WTP and WWTP can be used for toilet flush.

Progress Status

Delivered

Data Reliability

Self-declared

Funding Type

Public

Website Enterprise / Infrastructure

 www.themastermindcompany.nl

Sustainable Development

    ​TMMC installs the installation and does also operate it. We charge the client per treated m3 wastewater or per delivered recycle water.

    • ​Mitigation of water scarcity
    • Mitigation of logistic costs
    • Mitigation of polution

    ​Social regognation

    ​Reduction of water intake from well (or other sources) with 70-75%

    ​When used in combination with buffering, it makes resorts/hotels etc more independent in case of water supply problems

Testimony / Feedback

    ​Samples of treated wastewater were tested by the Dutch WaterLaboratorium, Haarlem, the Netherlands.

    The Waterlaboratorium is an accredited laboratorium.

Governance

    Ministers of Defense of the Netherlands

    Regional Authority

    The MasterMind Company

    Other

    J.H. Wissink

    Private

    At the request of the Dutch Ministry of Defence, the Master Mind has built a compact installation at the camp which treats the wastewater and makes drinking water from it. His company The MasterMind Company owns the installation and is paid by the Dutch Ministry of Defence for the treated cubic meters of water he supplies.

    ​Payment per m3 treated (waste)water

Sustainable Solutions

    Wastewater Treatment Plant with DIRECT POTABLE REUSABLE WATER

    TMMC's wastewater treatment plant (WWTP) treats waste water (black water) in 2 steps:

    • into indirect reusable water that can be infiltrated in the ground (water suitable for the production of drinking water) without pollution.
    • into DIRECT POTABLE REUSABLE WATER that can be used as an extra well for a Water Treatment Plant

    This system reduces the intake of fresh ground water with 70-75%

    Residu's of both WTP and WWTP can be used for toilet flush.

    • Economic development :
    • Smart city :
    • Urban project governance
    • Circular economy
    • Infrastructure
    • Waste management
    • Management of natural areas
    • Climate adaptation
    • Other
     https://www.construction21.org/data/sources/users/33258/greentech-2.pdf

Reasons for participating in the competition(s)

​The last two years we've engineered, built and serviced our Water Treatment Plant at the UN-camp in Mali. This is the first ever build Treatment Plant at this size. With this project we answer to the essence of our company; saving a source of the earth: water!

Building candidate in the category

Sustainable Infrastructure Grand Prize

Sustainable Infrastructure Grand Prize

Users' Choice

Users' Choice

Green Solutions Awards 2019 - Infrastructures
PDF

Share :
Author of the page

Jos Scheepens

R&D


Other case studies

More

Contest

Green Solutions Awards 2019 - Infrastructures