Community hall in Schweyen

7545
Last modified by the author on 27/08/2019 - 18:38

New Construction

  • Building Type : Other building
  • Construction Year : 2012
  • Delivery year : 2012
  • Address 1 - street : Place de la Carrière 57720 SCHWEYEN, France
  • Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season.

  • Net Floor Area : 345 m2
  • Construction/refurbishment cost : 673 344 €
  • Number of none : 1 none
  • Cost/m2 : 1951.72 €/m2
  • Primary energy need
    158 kWhep/m2.an
    (Calculation method : RT 2005 )
Energy consumption
Economical buildingBuilding
< 50A
A
51 à 90B
B
91 à 150C
C
151 à 230D
D
231 à 330E
E
331 à 450F
F
> 450G
G
Energy-intensive building
  • LQE 2013 prize winner

The municipality of Schweyen didn't have any meeting, nor convivial nor animation space. That’s why the City Council proposed the construction of a building, 300 square meters large, including a multi-purpose room of 200 square meters. The City Council has also opted for an innovative building in energy control and production.

 

Sustainable development approach of the project owner

- LQE 2013 prize winner
The municipality of Schweyen has opted for an innovative building in energy control and production.

Hygrothermal comfort
- Inertia of the envelope
- Airtightness and reduction of thermal bridges
- Passive solar gains
- Perspirant walls
- No feeling of cold wall
- Solar shadings
- Natural night ventilation by zenith chassis

Acoustic comfort
- Building distant of residential areas
- Acoustic equalizer materials (wood flooring, suspended ceilings, wood paneling)

Visual comfort
- Natural light evenly distributed (large windows, zenith windows)
- Wide views over the surrounding landscape and framed views of the forest
- Artificial lighting: nature and temperature of sources vary depending on areas (bar, centre of the hall, indirect atmosphere ...)

Low environmental impact building site
- Remote building site
- Building site charter
- Prefabrication and dry process.

Architectural description

The municipality of Schweyen didn't have any meeting, nor convivial nor animation space. That’s why the City Council proposed the construction of a approx. 300 square meters building, including a multi-purpose room of 200 square meters.

See more details about this project

 http://www.lqe.fr/home/upload/fiches/FicheSalleSchweyen.pdf

Stakeholders

    Contractor

    Commune de Schweyen (57)





    Thermal consultancy agency

    Utop





    Company

    Ettwiller


    Company

    Jung & Fils

Contracting method

Separate batches

Type of market

Global performance contract

Energy consumption

  • 158,00 kWhep/m2.an
  • 445,00 kWhep/m2.an
  • RT 2005

Envelope performance

    - Insulation: Backfill: 60 cm glass foam. Foundations: 14 cm of extruded polystyrene in periphery of the concrete slab. Walls & roof: 36 cm bundles of straw
    - Insulation: Straw, glass foam and extruded polystyrene
    - Glazing: low emission double glazing, Uw 1.1
    - Frontage: wooden cladding (larch)
    - Floors and walls: porcelain and oiled solid oak floor, earthenware and VOC-free paints

    EN 13829 - q50 » (en m3/h.m3)

  • 0,28

Systems

    • Heat pump
    • No domestic hot water system
    • Reversible heat pump
    • Single flow
    • Double flow heat exchanger
    • No renewable energy systems

Smart Building

    - Technical room with specific ventilation and independent access. External CABG. - Implementation of naturally durable wood (class 3) - Laminar flow hand dryers in the toilet - Referring person for adjusting installations

Urban environment

  • 345,00 m2
  • Location along the forest at "reasonable" distance from the town center for a pedestrian link.

Construction and exploitation costs

  • 87 894
  • 673 344
  • 375 988

Water management

    - Rain water collected in trench filter
    - Permeability of traffic areas (crushed stabilized, paving stones on a bed of sand and earth-stone)
    - Dual control flushing, automatic flushing urinals, flow restrictors, instantaneous water heaters under unit or close to the kitchen

Indoor Air quality

    - Internal finishings in untreated wood, VOC-free paints, earthenware and porcelain
    - Double-flow CMV on CO2 sensor

Life Cycle Analysis

    Wood (larch, oak); VOC-free paints; straw; glass foam